1-4) Preparing the ground for Ground Source Heat Pump underground piping. The whole of the garden is dug to a depth of 1.2m by Dennis, our expert digger driver, watched closely by Paula (Archaeologist) who is back with us executing her 'watching brief' over the project assisted by Ian, our builder).

GSHP4thumbGSHP2thumbGSHP3thumbGSHP6thumbthCenturyhandlethumb

5) Paula (Hawkeye) spots an intersting 13th-16th Century Medieval pot handle in the 'spoil' but up to now no ancient bones are found.

 
 GSHP8thumbGSHP7thumbGSHP9thumbMChamber1thumbMChamber2thumb
GROUND SOURCE HEAT PUMP PIPEWORK
MChamber3thumbMChamber4thumbGSHP10thumbMChamber6thumbMChamber5thumb1
evslogo

6-8) A total of 500 metres - 32mm Pipe laying @ 800mm apart followed by careful back-filling of trench.

9-12) Manifold Chamber constructed and partly installed by Scott, our ECOVISION SYSTEMS Engineer (helped by his canine assistant, Archie!).

13) Groundwork complete.

14-15) Manifold Chamber construction complete.

 
 
item5
item1

MAY 2008